My barn and arena are 15+ years old, but this is what we did. I’m in northern Michigan, so similar weather to you. We built in several phases. The barn came first, then the arena, which is attached to the barn by an enclosed "breezeway that allowed for some hay or equipment storage.
We were fortuante in several ways.
- Property is in the local gravel mining distrcit, so we were actually able to make use of lot of on site resources.
- Property was a dairy farm for a long time so we had a great layer of topsoil for good pasture growth and outdoor riding area, but it also had great drainage due to the underlying gravel.
- Site was relatively level, very minimal grading needed.
- Large local gravel and excavating company is less tha 5 miles down the road from us.
- Company had had experience with horse arena building. (They did the rings for Traverse City Equestrain show in its early and current days.)
We stared by having the barn shell built by an excellent local builder whose specialty was large pole barns.
When the shell was being built, we measured for the corner post of the stalls. They we 4X4 and installed at the time by the contractor.
Then we laid down “diamond dust” (the material used on ball diamonds) in two strips where the stalls would go, rented a compactor and compacted the surface level and near concrete hard. We did that labor ourself. It was a bit gruling, but in our younger days we were up to it. Now hittng age 70, not so much.
For the stall walls, we order several pallet loads of 12 foot southern yellor pine that was pre routed to stack on itself. We also ordered harware kits that were basically aluminum channes the the boards would slide into and we then screwed to each board. (Don’t ask me how many hours my tow kids and I spent with screw guns.) We also assembeld the sliding doors from kit harware. (My kids learned “measure twice, cut once”. Good math lesson; they were 9 and 14 at the time and became quite good at it.)
After the stalls were up, the contractor came back and pour and groved concrete for the aisle. That area was recess since the diamond dust for the stall flooring was built up in that process. When all was said and done it was a nice level floor. We put 4’x6’ mats, fitting snug, in the stalls.
The barn was completed in late spring.
A friend who had been through the process a few years before strongly encouraged putting down the arena base a year in advance, letting it sit exposed over winter settle well to see if it heaved at all. Then built the indoor over the “cured” surface. (Or if buget contraints mean it might take time to get to the indoor arena, you wil have an excellent out arena site in the mean time.)
Luckily no heaving occured.
Letting the base sit is, in my mind and experience, absolutely critical!!! A horse acquantance near by was in a hryy to get into the horse boarding business and skipped the waiting step. they lated admitted severely regretting that because they had constant problems with thier base even thought the materials used and thier soild conditions were very similar to ours.
For creating the base, we had the topsoil for the arena area and an adjacent area pushed aside and saved. The arena site was leveled, gravel was harvested from a large depression that was dug in the adjacent site and used for the coarse gravel layer, It coast use excavator time, but material was free, and of course no hauling charge. It is the hauling the is expensive far more than the material itself.
coarse gravel was leveled, then topped with IIRC 6 inches of diamond dust. That was laser leveled and compacted. Then it sat for the year noted above.
We proceeded with the indoor arean the next spring. Used the same contractor as the barn. He was a dream to work with an a wealth of knowledge of how to keep our overly picky building inspectors happy.
Once the arean shell was up, we ran a single course of treated 1x6 along the bottom where would be incontact with the footing material. the rest of the kickboard was, again, southern yellow pine that we installed ourselves.
Finally we had angular sand trucked in for the footiing. (You do NOT want beach sand.) IIRC it was called 10 A sand or something like that. I was able to go to the gravel pit and literally look at materials to make sure of what we would be getting. The sand itself wasn’t too costly and by luck of proximity the hauling wasn’t a total killer, but it was still about 80% of the bill even for the short distance.
The barn and arena have been my pride an joy over the years. It was worth evey once of sweat labor and patience it took to put it together.
Enjoy your project.